Brookline has launched a restoration project at Willow Pond and Leverett Pond in Olmsted Park, with dredging scheduled to begin this month.
The project will expand water capacity and enhance the health of the pond habitats, according to the Muddy River Master Oversight Committee. The committee described the effort as "restoring a living landscape in Olmsted Park, part of the historic Emerald Necklace." The full project is expected to be completed in the summer of 2027.
Willow Pond has not been dredged since 1963, according to @EmNecklaceBos on X. That Nov. 16 post said the dredging will improve water quality, reduce algae blooms and improve aquatic habitat.
Dredging at Willow Pond will remove accumulated sediment, and crews plan to install an outlet control structure and add new plantings. At Leverett Pond, the bank is proposed to be stabilized using a coir log, along with additional plantings, according to the town's project page.
Sam Downes, identified by the committee's website as Deputy Director of Engineering for the Town of Brookline, presented an overview of the project at the committee's Water Quality Subcommittee meeting on Jan. 28.
Planned schedule
The DPW's published schedule lists the following phases:
- Week of Nov. 9: Site preparation was scheduled.
- Week of Nov. 16: In-pond work was scheduled to begin, including water control and deployment of a small barge for hydraulic dredging. Hydraulic dredging was scheduled to start toward the end of that week.
- Nov. 23 through Dec. 31: Hydraulic dredging operations are planned, though the work may wrap up earlier.
- Winter 2026-2027: Sediment dewatering and testing.
- Late winter/early spring 2027: Sediment transport off-site. Timing depends on temperatures, because frozen sediment cannot be easily moved.
- Mid to late spring 2027: Site restoration, invasive species management around Willow Pond and buffer zone plantings around Leverett Pond.
Residents can find project documents and contact information on the town's Willow Pond project page.