Brookline has postponed public meetings on the Beacon Street Bridle Path project while it waits for a delayed base survey to wrap up.

The Beacon Street Bridle Path project would restore the historic median, originally designed by Frederick Law Olmsted in the late 19th century, as a multi-use path for cyclists, pedestrians and other non-motorized users. Angled parking and traffic lanes replaced the original bridle path decades ago.

According to the town's project page, the next meeting of the Design Review Committee was expected in the fall. That has not happened. The town cited "changes with the project team's subcontracted survey firm" that have affected the schedule, leaving the base survey of existing conditions along Beacon Street and portions of side streets incomplete.

The town said it does not plan to reconvene the committee or hold broader public engagement "until the survey information is finalized and available to support a productive discussion." The committee has met only once, on Oct. 9, 2025.

Other work continues in the meantime. The town's project page states the design team is still incorporating feedback from the Design Review Committee and a neighborhood Walk and Talk. The town is also coordinating with MassDOT and the Brookline Police Department to review crash history along Beacon Street and is coordinating with MassDOT on a Road Safety Audit.

The project spans 22 blocks between Ayer Road and St. Mary's Street. A parking utilization study completed in September 2025 counted approximately 1,250 on-street parking spaces along the corridor, including 650 curbside parallel spaces and 600 median spaces.

Toole Design Group, the project's design firm, completed a feasibility report and concept design that the Transportation Board approved. Toole's current scope advances the project through a 25% design public hearing and 75% design submission, according to the town.

The design work overlaps with a separate $51 million MBTA project on the same stretch of Beacon Street. The MBTA's Green Line C Branch accessibility project is upgrading seven stations along the corridor. Construction began in May 2026. The Tappan Street inbound and outbound platforms and the Englewood Avenue outbound platform have been built and returned to service. Temporary platforms remain in place at Dean Road and Summit Avenue, with work continuing on weekdays. The MBTA lists a spring 2027 target for completion.

A post on X on Nov. 11 flagged that $2 million in town spending is budgeted for fiscal years 2028 and 2029 for the bridle path's design phase, describing it as years five and six of design work with no plan yet shared publicly. The post questioned total costs, feasibility given MBTA needs, and potential impacts on trees, sidewalks and parking.

No date has been announced for the Design Review Committee's next meeting.