Crews at Charlesgate Park are building a new crossing over I-90 to restore walking and cycling paths lost decades ago.
The work is Phase One of the Charlesgate Park Revitalization Project. The Emerald Necklace Conservancy says the project will reconnect the Back Bay Fens to Charlesgate Park for the first time in decades. For Brookline residents who walk, run or bike the Emerald Necklace, the project promises a continuous path where a highway overpass and slip lanes now break the chain.
Charlesgate Park sits at the intersection of Boston's Back Bay, Fenway and Kenmore neighborhoods. Frederick Law Olmsted designed it as a link connecting the Emerald Necklace, the Charles River Esplanade and the Commonwealth Avenue Mall. Road construction over the decades covered the park with a highway overpass and divided it with roads and on-ramps, turning it into what the Conservancy describes as a pass-through space.
What's happening on the ground
New granite curbs are going in. They reveal the future layout of a narrower intersection with dedicated walking and biking paths, according to a construction update on the Muddy River Restoration Project site by Randall Albright of the Charlesgate Alliance and Jake Okrent of Landing Studio. The project removes slip lanes at the Boylston Street intersection to create new park space.
The new shared-use bridge is being built directly on top of the original stone abutments from H.H. Richardson and Olmsted's historic bridge. New light poles are being staged for installation along pedestrian pathways.
The Conservancy says the project also calls for more than 100 new trees and stormwater upgrades to help protect the Muddy River from pollution. When complete, the restored system would allow direct walking and cycling connections between the Emerald Necklace, the Charles River Esplanade and the Commonwealth Avenue Mall for the first time in more than five decades, according to the Conservancy.
How the project got here
Emerald Necklace Conservancy President Karen Mauney-Brodek helped found the Charlesgate Alliance in 2017. The group partnered with architecture firm Landing Studio on a conceptual design completed in 2019. That design was followed by $250,000 from the Commonwealth of Massachusetts and $400,000 from the Boston Community Preservation Act to fund a final, shovel-ready design, according to the Conservancy.
The Massachusetts Department of Transportation (MassDOT) indicated in 2021 that the bridge over I-90 would be replaced on an expedited timeline. The Charlesgate Alliance then commissioned Landing Studio to develop a proposal for a renovated bridge.
December tour
The Conservancy and the Charlesgate Alliance are offering a public tour in December for residents to see the construction firsthand. A specific date has not been announced. Registration is available on the Conservancy's website.